Floors, Cabinets, Paint or Trim: What Order Should a Remodel Go In?
Paint, cabinets, baseboards, appliances, carpet: where the new floor fits in a remodel, and the doors, dishwashers and stair risers that suffer when it goes in at the wrong time.
Winter is when a lot of central Indiana homeowners take on inside projects: a kitchen, a basement, fresh paint and new floors through the main level. When several trades are working in the same rooms, the order they go in matters. Put the floor in too early and it collects paint drips, ladder marks and dropped tools. Put it in too late, or in the wrong place relative to the cabinets, and you can end up with a dishwasher that will not come out or doors that drag. Here is the usual order, the decisions that change it, and what to ask before anyone starts. One thing to know up front: TFPros installs floors. We do not do cabinets, painting or plumbing, but we work alongside the people who do and can fit our dates around theirs.
The usual order
For most remodels it runs like this: demolition and removal; anything inside the walls, ceilings and subfloor, such as plumbing, electrical, ductwork and structural repairs; drywall; cabinets; painting; flooring; baseboards and trim; final paint touch-ups; appliances and fixtures back in; and carpet last of all.
The idea behind it is simple. Messy and heavy work goes first, the finished surfaces go last, and anything that has to sit on the finished floor goes in after the floor does. The two places where it genuinely varies are cabinets and baseboards, covered below.
Paint before the floor
Paint the walls and ceilings before the new floor goes in. Painting involves ladders, drop cloths, rollers and drips, and it is far easier to protect an old floor that is coming out anyway than a new one. Ceilings in particular spatter.
Baseboards and trim are the exception. If they are staying on the wall during the floor install, paint them first and expect a light touch-up afterwards where the new quarter-round or shoe molding meets them. If new baseboards are going in, they are usually painted after they are installed on top of the new floor, or primed and painted beforehand and touched up at the nail holes.
Cabinets and the floor: which goes first
There are two ways to do it, and both are common. The first is cabinets first: the cabinets are set on the subfloor and the new floor runs up to them. This uses less material and is the usual approach with floating floors, because most manufacturers say not to pin a floating floor under fixed cabinets or a heavy island. Floating, glue-down or nail-down explains why.
The second is floor first: the floor runs wall to wall and the cabinets sit on top of it. It is more common with nail-down hardwood and some glue-down floors. The advantage is that the floor is continuous, so a later layout change, a new island or a different cabinet footprint does not leave a gap in the floor. The cost is more material under cabinets nobody will see, and a finished floor that has to be well protected while the cabinets go in.
Either way, plan the heights. If the floor goes in after the cabinets, the finished floor is higher in front of them than underneath. That shortens the toe kick slightly and, more importantly, can trap the dishwasher, which has to slide out under the countertop for service. If the floor goes in first, the cabinets and countertop sit higher by the thickness of the floor. Neither is a problem when it is planned for. The best flooring for a kitchen covers the dishwasher and appliance openings we check at the measure.
Baseboards: leave them, or replace them after
If the existing baseboards are in good shape and the new floor is a similar height, they can usually stay. The new floor is fitted under them with an expansion gap where needed, and quarter-round or shoe molding covers the edge. Every install we do includes the quarter-round and transitions.
If the baseboards are being replaced anyway, take the old ones off before the floor goes in and install the new ones after. New baseboard set down onto a finished floor sits tight to it, and a floating floor still keeps the gap it needs at the wall. Where two floors meet goes into how edges and doorways are finished.
Doors, stairs and anything that depends on floor height
Interior doors are trimmed after the floor is in, once the finished height is known. A new floor that is thicker than the old one can make a door drag on the floor or catch on a rug. Door casings are usually undercut before the floor goes in so the floor slides under them rather than stopping short.
Stairs need the same thinking. If the floor at the top or bottom of a staircase gets thicker, the first or last step changes height relative to the others, which is a trip hazard. That is worth raising early if the project includes stairs. Hardwood stairs and landings explains how it is handled.
Appliances, toilets and fixtures go back last
Freestanding appliances like the refrigerator, range and washer and dryer go back in after the floor. Slide them in on a piece of hardboard or a furniture slider rather than dragging them across a new floor, and put protective pads under the feet.
In a bathroom the toilet comes up so the floor can run to the flange, and it goes back on a new wax ring once the floor is down. Bathroom and laundry room flooring covers why.
Carpet goes in last
Carpet is the most easily damaged surface in a remodel and the hardest to clean if it is. It goes in after the painters have finished, after the trim carpenter is done, and after the heavy items are back in the house. In a remodel where the main level gets a hard floor and the bedrooms get carpet, the hard floor usually goes in first and the carpet follows.
Protecting the new floor while work continues
If other trades will be working after the floor is down, cover it. A heavy, breathable floor protection board or paper made for the purpose is better than plastic sheeting, which is slippery and can trap moisture. Tape the protection to itself, not to the floor, because tape left on a finished floor can pull at the finish or leave residue.
Keep grit off it as well. Most scratches on a brand-new floor come from grit tracked in on boots and dragged under a ladder foot, not from anything dramatic.
Planning the dates
Give us the remodel schedule early, and tell us who else is working in the house and when. A floor install usually takes a few days for a typical main level, and we will tell you at the consultation how long yours should take and what needs to be done before we arrive. What happens during a flooring installation walks through the day.
We serve Carmel, Fishers, Indianapolis and the surrounding counties. Book a free in-home consultation and we will measure, check the subfloor and the heights that matter, and fit the floor into the rest of your project.
Frequently asked questions
- Should I paint before or after installing new floors?
- Paint walls and ceilings first, so the new floor does not collect drips and ladder marks. Baseboards that stay in place can be painted beforehand and touched up afterwards; new baseboards are usually installed on top of the finished floor and then painted or touched up.
- Do cabinets go in before or after the flooring?
- Both are common. With a floating floor, cabinets usually go in first and the floor runs up to them, because most manufacturers say not to pin a floating floor under fixed cabinets. With nail-down hardwood the floor is often installed first and the cabinets set on top. Either way, plan the floor height around the dishwasher opening.
- Should baseboards be removed before installing new floors?
- Not always. Baseboards in good shape can usually stay, with quarter-round or shoe molding covering the edge of the new floor. If the baseboards are being replaced anyway, remove them first and install the new ones after the floor so they sit tight to it.
- When should carpet go in during a remodel?
- Last. Carpet goes in after painting, trim work and any heavy items are finished, because it is the surface most easily damaged during construction and the hardest to clean.